Question: The method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS is known as: A. Alternative Analysis
The method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS is known as:
A. Alternative Analysis B. * Bottom-up Estimating C. Parametric Estimating D. Three-point estimating