Question: The project manager decided to improve the predicted completion date for the project by doing in parallel several of the activities that were scheduled to

The project manager decided to improve the predicted completion date for the project by doing in parallel several of the activities that were scheduled to be done in sequence. This is called:

A. Crashing B. Increasing priorities C. Fast Moving D. * Fast Tracking