Question: The reason that the schedule performance index (SPI) is shown as a ratio is to- A. Enable a detailed analysis of the schedule regardless of

The reason that the schedule performance index (SPI) is shown as a ratio is to-

A. Enable a detailed analysis of the schedule regardless of the value of the schedule variance B. Distinguish between critical path and noncritical path work packages C. * Provide the ability to show performance for a specified time period for trend analysis D. Measure the actual time to complete the project