Question: The recycling project manager has determined that the risks associated with handling certain hazardous chemicals are too high. He has decided to allow an outside
The recycling project manager has determined that the risks associated with handling certain hazardous chemicals are too high. He has decided to allow an outside company that specializes in handling hazardous materials to complete this portion of the project, and so has outsourced the handling of the chemicals to an experienced contractor.
Which of the following is it an example of?
A. * Transference B. Mitigation C. Avoidance D. None of the mentioned