Question: There are three main project roles on a PRINCE2 project board. Which of the following is one of them. A. The Project Senior B. The
There are three main project roles on a PRINCE2 project board.
Which of the following is one of them.
A. The Project Senior B. The Employee User C. * The Senior User D. The Project supplier