Question: Three-point estimating uses: A. * An optimistic, pessimistic, and most likely estimate to calculate the estimate. B. The weighted average of optimistic, pessimistic, and most

Three-point estimating uses:

A. * An optimistic, pessimistic, and most likely estimate to calculate the estimate.

B. The weighted average of optimistic, pessimistic, and most likely estimates to calculate the expected duration of the activity.

C. Dummy activities to represent logic links among three or more activities.

D. Free float instead of total float in the schedule calculations.