Question: To develop the WBS for the previously mentioned project, which ONE of the following is not a suitable task to be placed at the same
To develop the WBS for the previously mentioned project, which ONE of the following is not a suitable task to be placed at the same hierarchy with others?
A. Gather requirements B. Build the Lego objects C. Design the display D. * Build three TIE fighter objects