Question: Tucker is the construction project manager for a new school building. With six months left on the project, he is able to determine whether the
Tucker is the construction project manager for a new school building. With six months left on the project, he is able to determine whether the project is on target by using:
A. * forecasting.
B. performance review(s).
C. the cost management plan.
D. the earned value management.