Question: Walter is working on the program which contains a group of projects. Out of 8 projects, management has selected 2 projects and later on decided

Walter is working on the program which contains a group of projects. Out of 8 projects, management has selected 2 projects and later on decided to go for Project X, which would yield

$250,000 in benefits instead of project Y, which would yield $200,000. What is the opportunity cost for selecting project X over Project Y?

A. $50,000 B. $200,000 C. $250,000 D. $300,000