Question: What happens during Sprint 0? A. Overall planning, base system architecture, base design, version control and continuous integration setup B. Establish base system architecture and

What happens during Sprint 0?

A. Overall planning, base system architecture, base design, version control and continuous integration setup B. Establish base system architecture and design, install version control and continuous integration setup.

C. Base system architecture and design.

D. Requirements gathering, version control setup, and continuous integration setup.

E. * There is no such thing as Sprint 0.