Question: What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while
What is the term for an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level A. Decomposition B. * Rolling Wave Planning C. Alternative Analysis D. Reserve Analysis