Question: When a project falls seriously behind schedule, the most appropriate response is to: (a) Fire the project manager (b) Make the team work overtime (c)
When a project falls seriously behind schedule, the most appropriate response is to:
(a) Fire the project manager
(b) Make the team work overtime
(c) Add more people to the project
(d) Revisit the project plan