Question: When the project plan is broken down into tasks, what human resource allocations should be identified? A. Staff time, computer time, and task due dates

When the project plan is broken down into tasks, what human resource allocations should be identified?

A. Staff time, computer time, and task due dates B. * Staff working on project tasks, their roles and responsibilities, and task due dates C. Staff working on project tasks, billing rates, and task due dates D. Staff hours, billing rates, and marked-up material costs