Question: Which is correct? A. The critical path identified at the beginning of a project will never change in the progress of the project B. *
Which is correct?
A. The critical path identified at the beginning of a project will never change in the progress of the project B. * The critical path identified at the beginning of a project may change if some activities’ actual completion times are not as expected.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
