Question: Which is correct? A. The critical path identified at the beginning of a project will never change in the progress of the project B. *

Which is correct?

A. The critical path identified at the beginning of a project will never change in the progress of the project B. * The critical path identified at the beginning of a project may change if some activities’ actual completion times are not as expected.