Question: While conducting project kick-off meeting with the relevant stakeholders to communicate the start of the project, a key stakeholder diagrees with you on a decision
While conducting project kick-off meeting with the relevant stakeholders to communicate the start of the project, a key stakeholder diagrees with you on a decision you have made on the project. He even makes some comments against you in front of other stakeholders. As a project manager what should be your immediate response?
A. Do nothing in the meeting but later escalate this issue to the sponsor.
B. Take the help of other stakeholders and present your argument.
C. * Propose an immediate meeting between you and the key stakeholder to resolve the differences.
D. Ignore the key stakeholder and go ahead with your project.