Question: While EVM analysis, it was found that CPI of Project T2 is 0.95. What can be deduced from this data regarding the status of project
While EVM analysis, it was found that CPI of Project T2 is 0.95.
What can be deduced from this data regarding the status of project T2 A. Project T2 is running behind schedule B. Project T2 is running ahead of schedule C. Project T2 is progressing within the planned budget D. * Project T2 is exceeding the planned budget