Question: While reviewing the progress, the project manager assesses that an activity has been missed out from the implementation plan. A milestone, scheduled to be achieved
While reviewing the progress, the project manager assesses that an activity has been missed out from the implementation plan. A milestone, scheduled to be achieved within another week, would be missed with the current implementation plan. Which of the following is the next best action for the project manager in this situation?
A. Report the error and the expected delay B. Omit the status update on the milestone C. Report the error and the planned recovery actions D. * Assess alternatives to meet the milestone