Question: You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A schedule change has been requested. You know change
You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A schedule change has been requested. You know change from the perspective of the Perform Integrated Change Control is concerned with all of the following except which one?
A. Influencing factors that circumvent the change control process B. Issuing change requests C. Reviewing change D. Maintaining the integrity of baselines