Question: You are a project manager working for iTrim Central and youre preparing your cost management plan. You know that all of the following are true
You are a project manager working for iTrim Central and you’re preparing your cost management plan. You know that all of the following are true regarding this plan except for which one?
A. The WBS provides the framework for this plan.
B. Units of measure should be described in the plan usually as hours, days, weeks, or lump sum.
C. This plan is a subsidiary of the project management plan.
D. Control thresholds should be described in the plan as to how estimates will adhere to rounding ($100 or $1000 and so on).