Question: You are creating the projects Cost Baseline. Ultimately, what document will be the outcome of this process? A. Change Request B. * Budget C. Performance

You are creating the project’s Cost Baseline. Ultimately, what document will be the outcome of this process?

A. Change Request B. * Budget C. Performance Report D. Cost Control Accounts