Question: You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity

You are managing a software project. Your QA manager tells you that you need to plan to have her team start their test planning activity so that it finishes just before testing begins. But other than that, she says it can start as late in the project as necessary. What’s the relationship between the test planning activity and the testing activity?

A. Start-to-Start (SS)

B. Start-to-finish (SF)

C. * Finish-to-Start (FS)

D. Finish-to-Finish (FF)