Question: You are managing an internal project, the deadlines are set and work has been started. Senior management decides to finish the project sooner than planned.

You are managing an internal project, the deadlines are set and work has been started. Senior management decides to finish the project sooner than planned. You decide to start the project activities sooner and overlap some of them. This technique is called:

A. * fast tracking B. crashing C. rescheduling D. project collision