Question: You are reporting on project elements such as schedule status, deliverables completion, lessons learned, and resource utilization. Which of the following outputs of the Direct
You are reporting on project elements such as schedule status, deliverables completion, lessons learned, and resource utilization. Which of the following outputs of the Direct and Manage Project Execution does this describe?
A. Project management plan updates B. Deliverable C. Preventive action D. Work performance information