Question: You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently

You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except which one?

A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements