Question: You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?
A. PDM is also the AON diagramming method and it uses one time estimate.
B. PDM is also the AOA diagramming method and uses logical relationships.
C. PDM is also the ADM diagramming method and its most common logical relationship is finish-to-start.
D. PDM is also the GERT method, which allows for conditions, branches, and loops.