Question: You are working as a project manager for MALTEX, an IT organisation having a projectized organisation structure. You have recently started managing a project that
You are working as a project manager for MALTEX, an IT organisation having a projectized organisation structure. You have recently started managing a project that involves stakeholders from within and outside your organisation. The stakeholders external to your organisation are highly critical since the project negatively affects their interests. You are making serious efforts to gather their expectations and influence levels early in the project to ensure their voice is heard and proper communication needs can be planned in the project’s future phases. The outcome of your effort can be documented in:
A. * Stakeholder engagement plan B. Project scope statement document C. Project document D. Plan stakeholder engagement