Question: You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope because the glitch changed the characteristics of the product.

Which of the following statements is true?

A. Changes to product scope should be reflected in the project scope.

B. Changes to product scope should be documented in the scope management plan.

C. Changes to product scope will result in cost changes.

D. Changes to product scope are a result of corrective action.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!