Question: You are working on a project that will upgrade the phone system in your customer service center. You have used analogous estimating, parametric estimating, bottom-up
You are working on a project that will upgrade the phone system in your customer service center. You have used analogous estimating, parametric estimating, bottom-up estimating, and three-point estimates to determine activity costs. Which process does this describe?
A. Estimating Activity Resources B. Estimate Costs C. Determine Budget D. Estimating Activity Costs