Question: You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves 5 different sellers
You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves 5 different sellers and 20 members of your companyon the project team. You want to quickly review where the project now stands.
Which of the following reports would be the MOST helpful in finding such information?
A. Work status B. * Progress C. Forecast D. Communications