Question: You have prepared the WBS for your project. However, for your project, your company decided to try an agile approach. Many feel you will not

You have prepared the WBS for your project. However, for your project, your company decided to try an agile approach. Many feel you will not need to develop a WBS and a lot of other documents in your project management methodology. However, with agile the difference is-

A. Different levels of decomposition can be used B. * Epics are decomposed into user stories C. The WBS is represented as a hierarchical breakdown D. The project management element is not included because of the close customer collaboration