Question: You want to avoid scope creep on your project and are working hard to do so. Your sponsor has asked for regular reports as to
You want to avoid scope creep on your project and are working hard to do so. Your sponsor has asked for regular reports as to how the project is performing according to the scope baseline. You decide to use-
A. Variance analysis B. Inspection and peer review results C. * Work performance information D. The impact analysis results of proposed change requests