Question: Your project is experiencing resource constraints at certain times in the project timeline, requiring you to adjust start and finish dates on the schedule. What

Your project is experiencing resource constraints at certain times in the project timeline, requiring you to adjust start and finish dates on the schedule. What tool is best to use in this situation?

A. * Resource leveling B. Feeding buffer C. Critical Path method D. Resource smoothing