Question: Your project schedule was approved. Management has now mandated that the project be completed as soon as possible. However, you do not think it is
Your project schedule was approved. Management has now mandated that the project be completed as soon as possible. However, you do not think it is possible given resource constraints. In order to convince your management of your need for additional resources, you decide to use-
A. Resource manipulation B. Resource breakdown structure C. Critical chain scheduling D. * Resource leveling