Question: Your project scheduler has just started working with your project and has produced defective reports for the past two accounting cycles. If this continues, these

Your project scheduler has just started working with your project and has produced defective reports for the past two accounting cycles. If this continues, these defective reports could provide the potential for customer dissatisfaction and lost productivity that is due to rework. You discovered that the project scheduler needs additional training on using the scheduling tool that is used on your project. The cost of training falls under which one of the following categories?

A. Overhead costs B. Failure costs C. * Prevention costs D. Indirect costs