Question: Your team is reviewing the project activities and has started to estimate the duration of the work packages identified in the WBS. Some of these
Your team is reviewing the project activities and has started to estimate the duration of the work packages identified in the WBS. Some of these work packages and activities have significant uncertainty associated with them for which the team has created contingency buffers. The tool and technique that is used for this process is called:
A. Expert judgment B. * Reserve analysis C. Parametric estimating D. Three point estimating
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
