Question: Youre a project manager working in a weak matrix organization. Which of the following is NOT true? A. Your team members report to functional managers

You’re a project manager working in a weak matrix organization.

Which of the following is NOT true?

A. Your team members report to functional managers B. You are not in directly charge of resources C. Functional managers make decisions that can affect your projects D. * You have sole responsibility for the success or failure of the project