Question: 106. When a task is taking longer than the customer or the downstream process expects, which of the following activities should the team employ to
106. When a task is taking longer than the customer or the downstream process expects, which of the following activities should the team employ to resolve the issue?
a. Quality function deployment
b. Cycle time reduction
c. Takt time analysis
d. Is/is not matrix