Question: 6. In creating a risk priority number, what are the three scales that are calculated together? a. Cycle time, occurrence, priority b. Severity, range, priority

6. In creating a risk priority number, what are the three scales that are calculated together?

a. Cycle time, occurrence, priority

b. Severity, range, priority

c. Cycle time, range, detection

d. Severity, occurrence, detection