Question: A contractor in your locale, while working on a road project, submits a claim for extending the completion date due to adverse weather. His claim
A contractor in your locale, while working on a road project, submits a claim for extending the completion date due to “adverse weather.” His claim is based on the fact that heavy rain prevented work on the project for 13 days during the months of August and September. How do you respond to such a claim? Assume the following: Case I, you are part of the owner’s organization; Case II, you are part of the contractor’s organization.