Question: General Foundrys project crashing data are shown in Table 11.9. Crash this project to 13 weeks using CPM. What is the final time for each
General Foundry’s project crashing data are shown in Table 11.9. Crash this project to 13 weeks using CPM.
What is the final time for each activity after crashing?