Question: General Foundry's project crashing data are shown in Table 12.9. Crash this project to 13 weeks using CPM. What are the final times for each

General Foundry's project crashing data are shown in Table 12.9. Crash this project to 13 weeks using CPM.
What are the final times for each activity after crashing?
General Foundry's project crashing data are shown in Table 12.9.

TIME (WEEKS) COST (S) CRASH COST CRITICAL ACTIVITY NORMAL CRASH NORMAL 22,000 30,000 26,000 48,000 56,000 30,000 80,000 16,000 CRASH PER WEEK ($) PATH? 1,000 2.000 1,000 1.000 1,000 23,000 34,000 27.000 49,000 58,000 30,500 86,000 19,000 No Yes No Yes No Yes 2.000 3,000

Step by Step Solution

3.42 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path is ACEGH Total time is 15 weeks 1 Activities A C and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

162-M-S-P-M (23).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!