Question: General Foundry's project crashing data are shown in Table 12.9. Crash this project to 13 weeks using CPM. What are the final times for each
What are the final times for each activity after crashing?
.png)
TIME (WEEKS) COST (S) CRASH COST CRITICAL ACTIVITY NORMAL CRASH NORMAL 22,000 30,000 26,000 48,000 56,000 30,000 80,000 16,000 CRASH PER WEEK ($) PATH? 1,000 2.000 1,000 1.000 1,000 23,000 34,000 27.000 49,000 58,000 30,500 86,000 19,000 No Yes No Yes No Yes 2.000 3,000
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
The critical path is ACEGH Total time is 15 weeks 1 Activities A C and ... View full answer