Question: A control chart for nonconformities is to be constructed with c = 2.0, LCL = 0, and UCL such that the probability of a point
A control chart for nonconformities is to be constructed with c = 2.0, LCL = 0, and UCL such that the probability of a point plotting outside control limits when c=2.0 is only 0.005.
(a) Find the UCL
(b) What is the type I error probability if the process is assumed to be out of control only when two consecutive points fall outside the control limits?
Step by Step Solution
★★★★★
3.43 Rating (153 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
To solve this problem we need to analyze the control chart for nonconformities often referred to as a cchart with a certain average number of defects ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock