Calculate earned value performance parameters for each activity and for the cumulative project as of 11/7/14; fill
Fantastic news! We've Found the answer you've been seeking!
Question:
Calculate earned value performance parameters for each activity and for the cumulative project as of 11/7/14; fill in the table below:
S.V= Earned value - Planned value= E.V- P.V
S.P.I= Earned value/planned value= E.V/P.V
C.V= Earned value- Actual cost= E.V- A.C
C.P.I= Earned value/ Actual Cost= E.V/ A.C
a) Is the project ahead of schedule, on schedule, or behind schedule? What information are you using to make this assessment and why?
b) Is the project over budget, under budget, or on budget? What information is you using to make this assessment and why?
Related Book For
Posted Date: