Question: Calculate earned value performance parameters for each activity and for the cumulative project as of 11/7/14; fill in the table below: S.V= Earned value -

Calculate earned value performance parameters for each activity and for the cumulative project as of 11/7/14; fill in the table below:

Activity Activity One Activity Two Activity Three Activity Four Activity Five Activity

S.V= Earned value - Planned value= E.V- P.V

S.P.I= Earned value/planned value= E.V/P.V

C.V= Earned value- Actual cost= E.V- A.C

C.P.I= Earned value/ Actual Cost= E.V/ A.C

a) Is the project ahead of schedule, on schedule, or behind schedule? What information are you using to make this assessment and why?

b) Is the project over budget, under budget, or on budget? What information is you using to make this assessment and why?

Activity Activity One Activity Two Activity Three Activity Four Activity Five Activity Six Entire Project Schedule Variance (SV) 0 0 -2100 -3000 0 0 0.888 Schedule Performance Index (SPI) 1.000 1.000 0.400 0.824 -7600 Cost Variance (CV) -2000 3000 -2600 -6000 0 0 0.842 Cost Performance Index (CPI) 0.833 1.250 0.350 0.700

Step by Step Solution

3.36 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To analyze the projects status lets break down the provided data and assess each activity based on t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Corporate Finance Questions!