consider the following continuously operating job shop. Inter-arrival. Inter-arrival time of job are distribute as follows: Processing
Question:
consider the following continuously operating job shop. Inter-arrival. Inter-arrival time of job are distribute as follows:
Processing times for jobs are normally distributed, with mean 50 minutes and standard deviatio/ 8 minutes. Construct a simulation table and perform a simulation for 10 new customers. Assume that, when the simulation begins, there is one job being processed (scheduled to be completed in 25 minutes) and there is one job with a 50-minute processing time in the queue.
(a) What was the average time in the queue for the 10 new jobs?
(b) What was the average processing time of the 10 new jobs?
(c) What was the maximum time in the system for the 10 new jobs?