The field compaction curve for an earth dam project is given in the figure below The specification
Fantastic news! We've Found the answer you've been seeking!
Question:
The field compaction curve for an earth dam project is given in the figure below The specification requires that the soil be compacted at a water content within the range of 1% on the dry side of the optimum moisture content (OMC) and 2% on the wet side of OMC The contractor proposed that the water content specification would be satisfied if the air voids in the compacted soil were kept 7% of total volume With the assistance of appropriate calculations, comment critically on this proposal (POI WP1, C5 6%)