Question: Information concerning a product design project is given in table. Indirect project costs amount to $250 per day. The company will incur a $100 per

Information concerning a product design project is given in table. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts day 14.

Information concerning a product design project is given in tabl

a. What is the project€™s duration if only normal times are used?
b. What is the minimum costs schedule?
c. What is the critical path for the minimum costschedule?

PRODUCT DESIGN PROJECT DATA Normal Time (days) Crash Time (days)Crash Cost (S)Immediate Predecessor(s) Normal Cost (S) 1,000 800 600 1.500 900 1,300 900 500 Activity 1:200 2,000 900 2.000 1,200 1,400 900 900 A, B C, D

Step by Step Solution

3.39 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The AON diagram for the product design project is The critical path is BDEGH and the project du... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

227-B-M-L-O-M (910).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!