The Flapjack Corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour.
Fantastic news! We've Found the answer you've been seeking!
Question:
The Flapjack Corporation had 8,200 actual direct labor hours at an actual rate of $12.40 per hour. Original
production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor
standards were 7.6 hours per completed unit at a standard rate of $13.00 per hour.
Compute the labor time variance.:
a: 9,880F
b: 9,880U
c: 7,800U
d: 7,800F