Two critical path activities are candidates for crashing on a CPM network. Activity details are in the
Fantastic news! We've Found the answer you've been seeking!
Question:
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
Activity | Normal Time | Normal Cost | Crash Time | Crash Cost |
B | 4 days | $6,000 | 3 days | $8,000 |
C | 6 days | $4,000 | 4 days | $6,000 |
| | B; $2,000 |
| | B; $8,000 |
| | C; $1,000 |
| | C; $2,000 |