Question: If an activity duration cannot be estimated accurately, we should Use the average estimate in our critical path method Use the worst case estimate in

If an activity duration cannot be estimated accurately, we should

Use the average estimate in our critical path method

Use the worst case estimate in our critical path method

Move away from single point estimates and rely on 2 point (best and worst case) estimates

Move away from single point estimates and rely on a 3 point (best, worst and most likely case) estimates.