Question: If an activity duration cannot be estimated accurately, we should Use the average estimate in our critical path method Use the worst case estimate in
If an activity duration cannot be estimated accurately, we should
Use the average estimate in our critical path method
Use the worst case estimate in our critical path method
Move away from single point estimates and rely on 2 point (best and worst case) estimates
Move away from single point estimates and rely on a 3 point (best, worst and most likely case) estimates.