Question: What happens to the critical path in the network schedule created in question 5 if the duration of Task E changes to 11 days? Question

What happens to the critical path in the network schedule created in question 5 if the duration of Task E changes to 11 days?

Question 5

Create an activity on arrow diagram based on the following information:

Task A, duration 2, no dependency Task B, duration 4, no dependency Task C, duration 7, no dependency Task D, duration 5, depends on Task A Task E, duration 3, depends on Task B and Task C Task F, duration 8, depends on Task C Task G, duration 10, depends on Task D and Task E Task H, duration 4, depends on Task E Task I, duration 7, depends on Task F Task J, duration 12, depends on Task H and Task I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!